Floor & Wall Ltd were contacted by Willmott Dixon to help with surface cracking issues and concrete repairs on this multi storey car park which was part of a £30 Million transport hub.

Our team surveyed the deck and explained to the both Willmott Dixon and Lincoln Council that the original system needed to be removed and replaced, we presented our findings and after a tender process against other specialist contractors, Floor & Wall Ltd were chosen to carry out these essential works.

Voted "Best New Car Park" in 2019 British Parking Association Awards

Six-level multi-storey car park Part of the £30M Lincoln Transport Hub

10 Weeks 5000m2

Scope of works

  • Removal of original system for entire top deck and ramp
  • Concrete surface preparation of 5000m2
  • Heavy duty reinforcement bandaging over cracks
  • Concrete repair to areas of the deck
  • Installation of the Flowcrete Deckshield ED1 System inc HD Banding
  • Block bay marking throughout

Products / systems used

  • Flowcrete Deckshield ED1 System inc HD Banding
A fantastic project to be involved with and having worked with Willmott Dixon before we were happy to help technically on this car park to assist with problematic cracking issues, the fact it won "Best New Car Park" in 2019 was the cherry on the top!
Managing Director - Ian Crosbie

Floor and Wall Ltd, 1st
Floor, The Business Centre,
Normanby Road,
Scunthorpe, N Lincolnshire,
DN15 8QZ

+44 34435982374592347

hello@floorandwallltd.co.uk